MENU
Menu

AUDAX RENOVABLES: 20 MWp PHOTOVOLTAIC SYSTEMS LAUNCHED

Audax Renovables has obtained authorization to enter into operation the photovoltaic plants - with a total power of 20 MWp - of La Zarzuela I, II, III and IV, located near Toledo in the Spanish region of Castile-La Mancha. 

Although the works had been completed weeks ago, the commissioning of the plant suffered some bureaucratic-administrative delays.

 

A similar situation concerns the photovoltaic plants of Las Alberizas I, II, III and IV located in the municipality of Guadalajareño di Torija (Castile-La Mancha), with a total installed power of 20MWp: authorization from the institutions proposed as follows is also awaited for them to start producing energy. 

 

Furthermore, it should be noted that the Group continues with the construction of the following projects:

 

 

Their construction is progressing regularly, with an average execution of the 90%; the Audax Group expects its completion and entry into operation during this year.

 

All of the above projects did not require third-party financing, as the resources were derived from emissions green bonds made at the end of the previous year.

 

In the coming weeks, the Group will continue to promptly inform the market of the progress of the projects that make up the portfolio, with the aim of keeping its investors constantly updated.

 

Increasing the generation of 100% energy from renewable sources continues to be part of the strategy of the Audax Renovables Group, always focused on closing agreements with the aim of providing its customers with renewable energy produced in its own plants.

 

AUDAX RENEWABLES Trademark of Audax Energia Srl - Registered office Corso Tazzoli n. 235, 10135 Turin (TO) Turin Company Register REA To-1099939 - CF/VAT number 10027190015 - Share Capital: €100,000.00 fully paid up. Company subject to the management and coordination of Audax Renovables SA
phone-handsetcrosschevron down