AUDAX RENOVABLES: 20 MWp PHOTOVOLTAIC SYSTEMS LAUNCHED
Audax Renovables ha ottenuto l’autorizzazione all’entrata in esercizio degli impianti fotovoltaici – dalla potenza complessiva di 20 MWp – di La Zarzuela I, II, III e IV, situati presso Toledo nella regione spagnola della Castiglia-La Mancia.
Although the works had been completed weeks ago, the commissioning of the plant suffered some bureaucratic-administrative delays.
A similar situation concerns the photovoltaic plants of Las Alberizas I, II, III and IV located in the municipality of Guadalajareño di Torija (Castile-La Mancha), with a total installed power of 20MWp: authorization from the institutions proposed as follows is also awaited for them to start producing energy.
Furthermore, it should be noted that the Group continues with the construction of the following projects:
- Calañas, un progetto situato nell’omonima cittadina in provincia di Huelva (Andalusia), con una potenza di 4,48 MWp
- Los Arenales, located in the city of Polán, near Toledo, with a power of 5 MWp
- El Toconal, located in the city of Navalmorales, Toledo, with a power of 5 MWp
La loro realizzazione sta procedendo regolarmente, con un’esecuzione media del 90%; il Gruppo Audax ne prevede il completamento e l’entrata in esercizio nel corso di quest’anno.
All of the above projects did not require third-party financing, as the resources were derived from emissions green bonds realizzate alla fine dell’anno precedente.
Nelle prossime settimane il Gruppo continuerà a informare tempestivamente il mercato dell’andamento dei progetti che compongono il portafoglio, con l’obiettivo di tenere costantemente aggiornati i propri investitori.
Aumentare la generazione di energia 100% da fonte rinnovabile continua a essere parte della strategia del Gruppo Audax Renovables, sempre focalizzato sulla chiusura di accordi con l’obiettivo di fornire ai propri clienti energia rinnovabile prodotta nei propri impianti.